Demolition Permit in Moore, OK — Cost, Asbestos & Process
A demolition permit is required in Moore for the removal of any structure or part of a structure including detached accessory buildings, garages, sheds over 200 sq ft, and any portion of a primary dwelling. Even a partial demolition that affects load-bearing structure requires the permit. The Moore demolition permit fee is $50 residential and $100 commercial.
The single most important pre-demolition step is the Oklahoma DEQ asbestos NESHAP notification. Any structure built before January 1, 1990 must be inspected for asbestos by a state-licensed asbestos inspector before demolition begins. Friable asbestos must be properly removed by a licensed contractor before demolition. NESHAP notification to DEQ is required at least 10 working days before demolition begins, with a $250 minimum DEQ fee.
Utility disconnect verification is the second most-checked item: OG&E or OEC electrical disconnect, ONG (Oklahoma Natural Gas) gas service disconnect, and Moore Water Department water service disconnect. All three must be documented before the demo permit is issued. Sewer caps must be installed on any abandoned sewer lateral.
Who needs this permit
Is this permit required for your Moore project?
Any property owner or contractor demolishing a building, structure, accessory structure over 200 sq ft, or portion of a primary structure. Required even for storm-damaged structures (after emergency tarping and weather-tight repairs).
Moore cost range
Expected permit fees in Moore
Residential demolition: $50 flat. Commercial demolition: $100 flat. Asbestos NESHAP notification to DEQ: $250 minimum (paid to state, not city). Asbestos inspection / removal: $400-$5,000+ depending on findings.
Fees reference the current Moore Community Development fee schedule. Contact (405) 793-5053 to confirm for your specific project valuation.
Required documents
What Moore Community Development needs from you
- Moore demolition permit application
- Asbestos inspection report (required for any structure built before 1990)
- DEQ NESHAP notification confirmation (10-day advance)
- Utility disconnect verification: OG&E or OEC, ONG, Moore Water
- Site plan showing structures to be demolished
- Sediment / erosion control plan for the disturbed area (silt fence, inlet protection)
- Sewer cap installation plan
Process & timeline
Step-by-step process in Moore
- 1
Schedule and complete asbestos inspection (pre-1990 structures).
- 2
If asbestos found: licensed abatement before demolition.
- 3
Submit DEQ NESHAP notification at least 10 working days before demolition.
- 4
Coordinate utility disconnects with all utilities (allow 1-2 weeks for scheduling).
- 5
Submit Moore demolition permit application with all supporting documentation.
- 6
Permit issued — typically 3-5 business days after complete packet.
- 7
Demolition proceeds. Site must be secured with construction fencing if open more than 24 hours.
- 8
Final inspection: site graded, sewer capped, debris removed, erosion control intact.
Common reasons for rejection
Why Moore rejects demolition permit applications
- No asbestos inspection on pre-1990 structure
- No DEQ NESHAP notification (federal violation, not just local)
- Utility disconnects not verified
- Sewer cap missing or improperly placed
- Erosion control not in place before demolition begins
- Site not secured at end of work day if exposed for more than 24 hours
Skip the rejection cycle on your Moore demolition permit
Permitly analyzes your project against Moore Community Development requirements and generates a pre-filled application packet in under 3 minutes. First analysis is free.
Moore Community Development: (405) 793-5053 · 301 N Broadway Ave, Moore, OK 73160
Demolition permit FAQs — Moore, OK
Do I need an asbestos inspection to demolish my Moore garage?
If the garage was built before January 1, 1990, yes. The Oklahoma DEQ asbestos NESHAP rule applies to any structure of that age regardless of size or use. Inspection by a state-licensed asbestos inspector typically runs $400-$800.
How long does a Moore demolition permit take?
3-5 business days once the complete packet is submitted, including asbestos report and utility disconnect verification. Add 10 working days for DEQ NESHAP notification (parallel process; you can submit Moore permit while waiting).
Can I burn debris in Moore after demolition?
No. Open burning of construction debris is prohibited within Moore city limits. Debris must go to a licensed C&D landfill — the nearest are in southern OKC and Norman.